How Our Design Process Works: From Site Walk to Permit-Ready Plans
What happens between the first site walk and a signed construction contract: the Design Agreement, the plans, your selections, the permit, and the fixed bid.
Every project we build starts with two separate agreements: one for design and one for construction. The design phase is where the building, the permit, and the price get worked out together. Here is what happens in it, in order.
Before design: the free site walk
We meet at the property and walk it with you. We look at access, slope, utilities, and setbacks, and talk through what you want to build and how you will use it. Afterward you get a realistic cost range, so you can decide whether to go further before spending anything.
Step 1: The Design Agreement
If the range works, you sign a Design Agreement. It is a paid, stand-alone agreement that covers three things: the plans, the permit, and a fixed bid for construction. It does not commit you to build.
Step 2: Zoning and site information
We confirm the jurisdiction, the zone, and the size, height, and setback rules for your lot. We measure the site and locate the utilities. On septic properties, this is when the system's capacity is checked. Anything that could stop the project gets found here, on paper.
Step 3: Concept layout
You see a first layout: the footprint on your lot, the floor plan, and how the building looks from outside. This is the stage for big changes. Move the door, add a bay, turn the roof. Changes cost almost nothing now.
Step 4: Your selections
You choose how far we take it and what goes in.
| Scope level | What it means |
|---|---|
| Shell | A permitted, weather-tight building. You finish the inside. |
| Extended shell | The shell plus systems that are hard to add later, such as electrical service and insulation. |
| Full finish | Turn-key. Interior finishes, lighting, heat, and fixtures, ready to use. |
For finished spaces you also choose cabinets, flooring, tile, fixtures, and exterior materials. We narrow the options so the choices are manageable.
Step 5: Construction drawings
The layout becomes a full plan set: foundation, framing, elevations, sections, and details. If the structure needs an engineer, the engineering is done now and included in the set.
Step 6: Permit submittal
We prepare the application and submit the plans to the building department. We answer the plan reviewer's questions and make any corrections they ask for.
Step 7: The fixed, line-item bid
With final plans in hand, we price the project line by line. Permit fees and system development charges are shown separately and passed through at cost. This is the number that goes in the Construction Contract.
How long it takes
Plan on about 12 weeks from signing the Design Agreement to permit-ready plans. Two things move that: how quickly selections get made, and how long the building department takes to review.
What you have at the end
- A complete set of plans, which are yours to keep.
- A permit, or a permit application in review.
- A fixed, line-item price for construction.
What we need from you
- How you will use the building. It shapes every decision after it.
- A budget range. It lets us design to a number instead of guessing.
- Timely decisions. Selections made on schedule keep the 12 weeks at 12 weeks.
When you are ready to start, request a site walk. For what happens after the contract is signed, see the ADU design-build process.
Common questions
Do I own the plans?
Yes. The plans produced under the Design Agreement are yours to keep, whether or not you go on to build with us.
Do I have to build with Friday Design Build after the design phase?
No. The Design Agreement and the Construction Contract are separate. Most clients continue, because the plans and the price were developed together, but you are not obligated to.
What does the design phase cost?
It depends on the size and complexity of the building. You get the Design Agreement price in writing after the site walk, before you commit to anything.
Reviewed November 2026. This guide describes how Friday Design Build works. Timelines depend on your selections and on building department review.
Keep reading
Related guides
The Oregon ADU Design-Build Process: From First Site Walk to Final Inspection
Understand the steps to plan, permit, price, and build a custom ADU in Clackamas County with fewer expensive surprises.
Read guide →What Does It Cost to Build an ADU in Clackamas County?
A practical ADU budget guide for Clackamas County. Learn what construction, utilities, permitting, sitework, and contingency may include.
Read guide →Garage, Shop, or ADU: Which Backyard Building Is Right for Your Property?
Compare detached garages, workshops, and legal ADUs in Clackamas County. Learn why intended use changes design and permits.
Read guide →Before you build
Start with the actual property.
Send us the address, what you want to build, and anything you already know about the site. We'll tell you what applies and what the next step is.
Or email erich@fridaydesignbuild.com